Case Note: Cheungs Construction Ltd v KCM Properties Ltd & Ors (Court of Appeal, Solomon Islands, 31 May 2024)

  1. Citation:


Cheungs Construction Ltd v KCM Properties Ltd, Guadalcanal Provincial Assembly, Attorney General (Solomon Islands Court of Appeal, 12 of 2023, Decision Date: 31 May 2024).

  • Court:


Solomon Islands Court of Appeal.

  • Judges:


Muria P (President), Gavara-Nanu JA, Lawry JA.

  • Counsel:


Appellant/Cross-Respondent (Cheungs Construction Ltd): F. Waeta’a

Respondent/Cross-Appellant (KCM Properties Ltd): J. Apaniai

  • Nature of Case:


Appeal against a High Court assessment of damages awarded to KCM (First Respondent) following a successful counterclaim in 2010. KCM cross-appealed the quantum.

  • Material Facts:
  • 2003: Cheungs (Appellant) sued KCM, obtained an interim injunction stopping construction on land (PN 191-023-136).
  • 2010: High Court (Goldsbrough J) dismissed Cheungs’ claim, upheld KCM’s counterclaim, ordered damages to be assessed, and awarded costs ($53,200) against Cheungs (unpaid).
  • 2015: KCM applied for damages assessment.
  • 2023: High Court (Keniapisia J) assessed damages at SBD $10 million for KCM (plus costs).
  • Appellant’s Grounds: (1) Denial of right to appeal 2010 judgment due to lack of reasons; (2) Erred requiring formal application for written judgment; (3) Damages excessive/remote; (4) Award inconsistent with report uncertainties.
  • Respondent’s Cross-Appeal: Challenged the reduction from claimed $52.06m to $10m, citing errors in evidence interpretation, construction period neglect, remoteness misapplication, inadequate reasons, expert testimony weight, and adversarial process failure.

7. Legal Principles Applied:

  1. Remoteness of Damages: Applied Attorney General of the Virgin Islands v Global Water Associates Ltd [2020] UKPC 18 (Privy Council):
    1. Damages aim to put the injured party in the position they would have been in had the wrong not occurred (compensatory principle).
  • Recoverable loss must be a type reasonably contemplated as a serious possibility at the time of the breach/wrong.
  • Contemplation is objective – what the defendant must be taken to have contemplated, based on knowledge at the relevant time.
  • Test is factual.
  • Assessment of Damages:
  • Unchallenged expert evidence (where no cross-examination or counter-evidence is offered) is generally accepted.
  • Courts must provide reasoned calculations for significant reductions.
  • Future loss of profit (e.g., lost rent) is recoverable if foreseeable, even if the project is ultimately not undertaken post-injunction.
  • Damages for lost gross income must account for taxation – awarding untaxed gross profit would unjustly enrich the claimant.
  • Expenses not actually incurred (like increased building costs if building doesn’t proceed) are too remote.

8. Ratio Decidendi (Reason for Decision):

  1. Appeal Dismissed:
  • Grounds 1 & 2: Were challenges to the 2010 judgment, not the 2023 damages assessment. No appeal filed in 2010; now out of time. Irrelevant to the current appeal.
  • Ground 3 (Remoteness): The loss of future profits (rent) due to the injunction preventing construction was reasonably foreseeable as a serious possibility when the injunction was obtained (construction had started). Privy Council principles applied.
  • Ground 4 (Report Uncertainties): While reports contained uncertainties, the Appellant failed to challenge them via cross-examination or provide counter-evidence. The Judge was entitled to make some reduction based on identified issues, but the method of reduction was flawed (see Cross-Appeal).
  • Cross-Appeal Allowed:
    • The High Court fundamentally miscalculated damages due to a misunderstanding of the evidence:
      • Mistakenly believed the MUSA report covered 13 years (2003-2016) instead of the correct 7.5-year loss period (Jan 2005 – Jun 2012).
      • Reduced claimed $57.06m to $28m based on this error.
      • Further reduced to $10m without a reasoned basis for the $18m deduction.
  • The Court of Appeal reassessed damages at SBD $18,221,097.40, applying:
  • Reduced rental rate ($150/sq m flat) to account for overstated rent and annual increases.
    • 15% reduction for vacancy (midpoint of expert range).
    • 30% deduction for income tax (on net rent forgone).
    • Disallowed claimed building cost increases ($4.94m) as KCM didn’t build and thus didn’t incur the loss.
    • Allowed building reassessment fee ($89,431.40) as actually incurred.
    • Disallowed legal fees (covered by 2010 costs order).

9. Obiter Dicta (Other Remarks):

  1. The Appellant’s procedural failures (not appealing the 2010 judgment promptly, not cross-examining experts, not providing counter-evidence during assessment) severely hampered its case and left the lower court with unchallenged evidence.
  • The undertaking in damages given when obtaining the injunction inherently acknowledged the foreseeable risk of loss if the injunction was later found wrongful.
  • The mere passage of time without the claimant developing the land post-injunction does not automatically make lost profit claims remote if the loss during the injunction period was foreseeable.
  • Detailed reasons are required when a court makes substantial reductions from claimed damages, especially when based on perceived weaknesses in evidence.

10. Key Takeaways:

  • Foreseeability is Key for Remoteness: Loss of future profits from prevented development is recoverable if it was a reasonably foreseeable consequence of the wrongful act (e.g., an ultimately unjustified injunction) at the time it was obtained.
  • Active Participation in Assessment is Crucial: A party challenging damages evidence must cross-examine experts and/or provide credible counter-evidence. Failure to do so risks the evidence being accepted largely unchallenged.
  • Damages Calculations Require Rigor & Transparency: Courts must base calculations on a correct understanding of evidence and provide clear reasoning for significant adjustments, especially large reductions.
  • Taxation Matters in Profit Loss Claims: Damages for lost net profit must account for the tax that would have been payable on the income; awarding gross profit unjustly enriches the claimant.
  • Unincurred Costs are Not Recoverable: Damages cannot be claimed for increased costs (e.g., building costs) if the claimant never actually incurred them by proceeding with the project.
  • Procedural Deadlines are Binding: Challenges to a judgment’s substance (like lack of reasons) must be pursued promptly via appeal; raising them years later in a separate proceeding (like damages assessment) will likely fail.

Orders:

  1. Appeal dismissed.
  2. Cross-appeal allowed.
  3. High Court assessment ($10m) set aside.
  4. Appellant (Cheungs) to pay Respondent (KCM) damages of SBD $18,221,097.40.
  5. Appellant to pay Respondents’ costs.

Related Posts